INSTALLATION OF 11 KV LINE
STEPS TO BE FOLLOWED: 1.Take up survey and Route finalization Conduct detailed route survey to minimize bends,Crossings and obstacles Obtain Statutory clearance for forest,Railways and highways if any. Prepare Route map and Pole schedule 2.Foundation and Erection Supports Type of support: PCC poles (8/9/11 m), steel tubular poles, or lattice towers depending on span & […]